04 · work · proposal
Winning an energy-sector proposal
I led the engineering proposal and pitch, owning the team plan and timeline. We won the bid, and the account grew into four further projects and staff augmentation.
Role: VP of Engineering, Teravision
My role
Pricing, margin and contracts belong to Commercial and finance. I led the team that prepared the engineering proposal and the pitch. I owned the timeline, the team numbers and the estimating tool, and once we won, the project budget.
The situation
An energy company ran an RFP for a new application. Its existing system ran on .NET, kept operations running reliably and held years of business rules that were hard to maintain. Vendors and clients needed a new way in. Phase one was a standalone application with its own database and a service layer that consumed APIs exposed by the backend.
Like any RFP, it started with limited information. We still had to propose an architecture and explain why.
What we proposed
The client worked in the Microsoft ecosystem. As a team we agreed to present .NET for the backend and React for the front end. That kept the client in their ecosystem and gave them well-maintained components in the front end.
For the estimate we used a tool I had built years earlier. We listed the stories and features as line items and sized each one on a t-shirt scale. The tool converted sizes to hours by layer: backend, front end and DevOps. Every assumption was documented. When we changed the team, the tool recalculated the timeline.
With Commercial, we agreed to support a more aggressive timeline and to add experienced bench engineers beyond what the client required. The scope was closed, so the client cared about the delivery date and the result. The extra people reduced risk and made the shorter calendar credible.
What happened
We won. Phase one finished a little past our aggressive plan. A client-paid change request explains part of the gap, and the rest was our own slip.
The client then gave us four more projects, including AI work and smaller integrations. The relationship later moved to staff augmentation, with part of the team placed with the client. The account became a major one for the company. The proposal, the win and the growth that followed were the team’s work.